PROJECT SUMMARIES
Dekalb Energy Canada Ltd. This facility was destroyed by fire. The following complete EPCM services were provided. A temporary by-pass system was installed to enable the sweet natural gas plant to supply Nova (accomplished in three weeks). The main process building was completely rebuilt; the damage to the compressor buildings was repaired, as well as the field office. Plant capacity rated at 14.5 MMSCF/D (accomplished in five weeks). This work included metallurgical analysis and hydro-test for damaged equipment to the satisfaction of the Boilers' Branch, confirmation of process design, generation of all field construction isometric, PLC programming, start-up and commissioning. Click on a thumbnail below to view picture: